Concrete Shoulder Work on Randy Jay to begin 10/25/21
Updated 10/21/2021: SD Ellenbecker is expected to begin the concrete shoulder work on Monday, October 25th. They will be working on pouring driveway approaches right after and paving of the street is anticipated to be at the end of the week, weather permitting.
Asphalt Paving Schedule
Updated 10/7/2021: American Asphalt is planning to pave the first layer of asphalt on Kirk St, E Everest, Robin, Rodney and Douglas from Robin to Kirk starting Thursday, October 7. The plan is to get all of these streets paved between 10/7 and 10/9, with paving to occur on Saturday if needed. The roads will be open to local traffic during this time and they will have Flagger's directing traffic around the paver.
E Jelinek Road Closure
Updated 9/28/2021: E Jelinek between Randy Jay and Rodney will be closed thru the end of the day, Wednesday September 29th to finish storm sewer installation. E Jelinek is then expected to be open to local traffic then for the remainder of the project.
Concrete work on E Everest, Douglas, Kirk and Robin
SD Ellenbecker will be pouring curb and concrete aprons the week of September 20 and concrete work will last through the end of September. Please park on the odd side of the road (east or south) depending on street to allow traffic to make it through.
Concrete work to begin Monday, August 9.
UPDATED Thursday, August 5. Concrete work has been moved to Monday, August 9.
Residents on Rodney and Kirk (from E Jelinek to Douglas), please note the concrete curb/shoulder work is planned to start Monday, August 9. Any vehicle you may need for the following 7-10 days you’ll need to have out of your garage/driveway as the concrete will need time to cure after being poured. The day of pouring the contractor will notify you directly by knocking on the door/ringing the doorbell. Please plan on having your vehicles parked on E Jelinek or another side street for the day while the concrete work is being performed. Once the work is completed you can park on the road again in front of/across from your house, just be careful not to drive over/into the new curb. Please park your vehicles only on the east side of the road (in front of the houses with an odd number (1, 3, 5, 7, 9). With the concrete curing, the driving lanes will be narrow and parking on both sides of the road will end up making the road impassable..
April 28, 2021 Special Assessment Hearing
The Special Assessment Meeting will be held on April 28, 2021 at 6:00 PM at Dales Weston Lanes, 5902 Schofield Avenue, Weston, WI 54476.
Linked documents for the Special Assessment Hearing are below:
February 10, 2021 Public Information Meeting
A Public Information meeting for the Crestwood Acres Reconstruction Project was held Wednesday, February 10. Materials from the meeting are linked below.