How much will the project cost?

The current estimated project cost is $16.6 M.  The building itself accounts for $14.4 M of this cost.  The land purchase, which was not in the original project estimates, accounts for $1.0M of the total project.  The balance of $1.2 M is in site preparation, shop equipment, architect’s fees, furniture, and contingencies.

Show All Answers

1. Why do we need to replace our Municipal Building?
2. Was renovation of the existing building(s) considered?
3. How much will the project cost?
4. The original facilities study in 2016 estimated the project would cost between $12 and $13 million. Why has the estimate gone up to possibly 15 million?
5. How will the project affect my taxes?
6. If we don’t construct the new building will my taxes remain the same or even go down?
7. Why was a new site selected?
8. What will we do with the existing site and the buildings?
9. How does the new facility compare to the current one?
10. Will the new building include technology which improves energy efficiency and conservation of resources?
11. Will this be built by local businesses and contractors as to keep money in the local economy?
12. Does this project require a referendum?
13. In summary, has the need for this project been adequately evaluated?