Construction Updates

6/16/2021:

The schedule for the contractor’s activity for each phase/street is below, please keep in mind activities are weather dependent and the schedule may change:

 

  • Phase 1: Rodney St
    • This week: The contractor finished installing water and sewer laterals.  All water and sanitary sewer work on Rodney is now complete.  WPS has begun replacing the gas main and services.  
    • Next week: WPS should finish up the gas main and service replacements.  Switlick may return later next week to begin storm sewer.

 

  • Phase 2: Kirk St and E Everest Ave (Kirk St to the Water Tower)
    • This week: Temporary watermain connections were made.  A water valve at Kirk and E Jelinek was replaced today.  Switlick began removing asphalt on Kirk in preparation for replacing the sanitary sewer beginning Thursday.
    • Next week: Switlick will continue to replace the sanitary sewer main starting at E Jelinek and heading south towards E Everest.

 

  • Phase 3: Douglas (Kirk to Robin), Robin and E Everest (west of Kirk St)
    • This week: Nothing Planned
    • Next week: Nothing Planned

 

  • Phase 4: Douglas (Camp Phillips to Robin), Randy Jay
    • This week: Nothing Planned
    • Next week: Nothing Planned


6/9/2021:

The schedule for the contractor’s activity for each phase/street is below, please keep in mind activities are weather dependent and the schedule may change:

 

  • Phase 1: Rodney St
    • This week: Once the crew gets the watermain break fixed, they will finishing up the sanitary sewer and water and sewer laterals on Rodney near Douglas.  They will then come back towards E Jelinek and connect water and sewer laterals for the houses on Rodney that are still on temporary water.  
    • Next week: If there are still laterals left to be connected on Rodney, those will be finished up early next week.  They have experienced a delay in the storm sewer structure delivery and if the structures show up, the crew will then install storm sewer on Rodney.  If the storm sewer structures aren’t delivered by Monday, the crew will begin work on Kirk St sanitary sewer to keep moving on the project.

 

  • Phase 2: Kirk St and E Everest Ave (Kirk St to the Water Tower)
    • This week: Temporary watermain was installed and filled.
    • Next week: The contractor will work on getting the temporary water connections to houses made, also additional topsoil striping and asphalt removal will occur.  As noted above for Rodney St, if the storm sewer structures aren’t delivered by Monday, the crew will begin working on the new sanitary sewer main on Kirk St Monday morning.

 

  • Phase 3: Douglas (Kirk to Robin), Robin and E Everest (west of Kirk St)
    • This week: Utility relocations should be finishing up
    • Next week: Possible topsoil stripping to occur.

 

  • Phase 4: Douglas (Camp Phillips to Robin), Randy Jay
    • This week: Nothing Planned
    • Next week: Nothing Planned


6/2/2021:

The schedule for the contractor’s activity for each phase/street is below, please keep in mind activities are weather dependent and the schedule may change:

 

  • Phase 1: Rodney St
    • This week: The crew is finishing up watermain and fire hydrant installations today and will begin working on installing the new sanitary sewer starting tomorrow (Thursday).  They will continue with the sanitary sewer as well as water and sewer laterals within the road right of way for the remainder of the week.
    • Next week: The crew will continue installing the sanitary sewer along with water and sewer laterals and should be close to finishing up by the end of the week.

 

  • Phase 2: Kirk St and E Everest Ave (Kirk St to the Water Tower)
    • This week: Topsoil was removed and the temporary watermain was installed.
    • Next week: The contractor will work on getting the temporary watermain operational.

 

  • Phase 3: Douglas (Kirk to Robin), Robin and E Everest (west of Kirk St)
    • This week: Utility relocations should be finishing up
    • Next week: Nothing Planned

 

  • Phase 4: Douglas (Camp Phillips to Robin), Randy Jay
    • This week: Nothing Planned
    • Next week: Nothing Planned

5/26/2021:

The schedule for the contractor’s activity for each phase/street is below, please keep in mind activities are weather dependent and the schedule may change:

 

  • Phase 1: Rodney St
    • This week: The street is on temporary water and the contractor is currently replacing the existing watermain with the new watermain.  This work is expected to continue throughout the end of the week.
    • Next week: The crew will finish watermain installation as well as installation of new fire hydrants and then begin working on the sanitary sewer as well as water and sewer laterals.  This work will progress from E Jelinek Ave south towards Douglas Ln.

 

  • Phase 2: Kirk St and E Everest Ave (Kirk St to the Water Tower)
    • This week: WPS was working on gas line replacements and it sounds like this will continue into next week.  
    • Next week: If WPS is done with their utility relocations, the contractor will start on the removal of topsoil in preparation for the temporary water pipes.

 

  • Phase 3: Douglas (Kirk to Robin), Robin and E Everest (west of Kirk St)
    • This week: Utility relocations should be finishing up
    • Next week: Nothing Planned

 

  • Phase 4: Douglas (Camp Phillips to Robin), Randy Jay
    • This week: Nothing Planned
    • Next week: Nothing Planned


5/19/2021:

The schedule for the contractor’s activity for each phase/street is below, please keep in mind activities are weather dependent and the schedule may change:

 

  • Phase 1: Rodney St
    • This week: Temporary water is being setup and the crew will be working on connecting each water lateral to the temporary water service.  The crew will be connecting to your underground lateral so there won’t be a hose running above the ground.  There will be some intermittent water outages while these connections are made.
    • Next week: The crew will finish temporary water if needed and then begin working on the sanitary sewer installation.  Work will progress from E Jelinek Ave south towards Douglas Ln.

 

  • Phase 2: Kirk St and E Everest Ave (Kirk St to the Water Tower)
    • This week: Later this week the crew may be starting to remove topsoil in preparation of the temporary water setup.  However, WPS appears to still have some relocation work to complete so this may not occur until the following week.
    • Next week: If WPS is done with their utility relocations, the contractor will start on the removal of topsoil in preparation for the temporary water pipes.

 

  • Phase 3: Douglas (Kirk to Robin), Robin and E Everest (west of Kirk St)
    • This week: Utility relocations are ongoing
    • Next week: Utility relocations should be finishing up

 

  • Phase 4: Douglas (Camp Phillips to Robin), Randy Jay
    • This week: Nothing Planned
    • Next week: Nothing Planned