Phase 1: Ryan St to Progress Way
6/9/23 Update: The contractor has completed most of the tree clearing for the phase and has begun working on the storm water pond construction between Zinser St and Progress Way. On Monday, 6/12, the contractor is planning to begin the sanitary sewer work starting at Zinser St and then heading west towards Ryan St. Traffic should limit their use of Weston Ave between Ryan St and Zinser St for the next several weeks as utility installation progresses along this stretch.