Construction Updates - West Phase

CAMP PHILLIPS RD (CR-X) TOWARD VON KANEL ST - SEGMENT 1

EARLY SEPTEMBER 2024:

The Contractor (Integrity Grading & Excavating) plans to begin work along the project corridor.

The construction zone remains open only to local traffic going to and from their homes. Through traffic is advised to follow speed limits and follow the signed detour route. This is for the safety of all our residents and the Contractor's crews helping our community complete this important infrastructure project.

WEEK OF:

SEPTEMBER 9, 2024

Tree clearing, grubbing, and removals will continue for most of this week with roadway work beginning later in the week. Traffic control and detour signs will be installed as the street will be closed to through traffic.

SEPTEMBER 2, 2024 (AFTER LABOR DAY)

Weston Avenue Reconstruction project begins. Contractor will be mobilizing equipment and materials to the project area and begin clearing, grubbing, and removals. Traffic control and detour signs will be installed as the street will be closed to through traffic.