Weston Ave and Alderson St

Project to begin the week of June 17

- Phase 1: Weston Ave and Alderson St Intersection and Alderson St 

  • Estimated Schedule: 6/17/24 thru 8/27/24
  • Consists of the reconstruction of the Weston Ave and Alderson St intersection along with Alderson St from Weston Ave to Summit Ave.  Included with this work is replacement of watermain and sanitary sewer.

- Phase 2: Summit Ave 

  • Estimated Schedule: 8/28/24 thru 11/18/24): 
  • Consists of the repaving of Summit Ave, installation of new watermain and some storm sewer addition.

- Phase 3: Weston Ave (Alderson St to Birch St)

  • Estimated Schedule: 9/3/24 thru 11/18/24): 
  • Consists of the repaving of Weston Ave, installation of new watermain and construction of a multi-use path on the south side of the road.