SEPTEMBER 2024:
Haas Sons is the Contractor awarded the construction contract.
LATE SEPTEMBER 2024:
Preconstruction meeting takes place with the Village, Field Engineer, and Contractor as preparations begin to start construction in the following weeks.
Thank you for your patience and cooperation during construction of our Village infrastructure improvement project.
WEEK OF:
OCTOBER 14, 2024
The Contractor has installed traffic control along Schofield Avenue closing the outside travel lane. Work related to installing the concrete bases for the new traffic signals continues this week. The Contractor may begin working on concrete pavement removals and replacements as construction of traffic signal bases progresses.
OCTOBER 7, 2024
Schofield Avenue and Mesker Street Intersection Improvement project begins. Contractor will be mobilizing equipment, materials, and installing erosion control as the prepare to start on demolition and removal-related work.