Construction Updates

Thank you for your patience and cooperation during construction of our Village infrastructure improvement project.

WEEK OF:

JUNE 9

The north side of the Schofield Ave and Alderson St intersection will be closed to through traffic to complete removals and construction of new water main, signal bases, curb and gutter, and grading.

JUNE 2

Spot curb and gutter will be constructed along with driveways and sidewalk along the corridor between Normandy St and Birch St.

MAY 26

Curb and gutter will begin to be placed between Alderson St and Birch St. Sidewalk removals and driveways will be prepped for new concrete. Utility structure repairs will be completed.

MAY 19

Curb and gutter will begin to be placed between Normandy and Alderson St. East of Alderson road building and median work will continue.

MAY 12

Pavement removal to just east of Birch St was completed.  Road building between Normandy St and Alderson St continued.  Sewer and water work near Fox St was completed as well.

MAY 5

Pavement removal will continue.  Additional water valve replacements will be completed between Normandy St and Alderson St.

APRIL 28

Traffic will be moved to the eastbound lanes with concrete pavement removals to begin starting at Normandy St and proceeding to the east along the westbound lanes.  Water valve replacement between Normandy St and Alderson St is expected to begin as well.

APRIL 21

Temporary signal work will continue.  Bi-directional traffic control in the eastbound lanes to be installed to get the eastbound lanes ready for 2-way traffic.

APRIL 14

Temporary lane closures will be used for the installation of the temporary signal lights at Alderson, Target/Ace and Birch St.

APRIL 2025:

Contractor plans to begin installing traffic control, erosion control devices, temporary traffic signals, and begin pavement removals along the project corridor.

MARCH 2025:

Haas Sons Inc. is the Prime Contractor awarded the construction contract.