Village of Weston Building
view the original message here
Village Meetings

Upcoming Meetings: 
Sept 4th - Sept 11th

  • Public Works & Utility Committee, September 8th, 4:30 p.m.
  • Plan Commission, September 8th, 6:00 p.m.
  • Board of Trustees Budget Workshop, September 9th, 4:00 p.m. 
  • SAFER Board of Directors Meeting, September 9th, 5:30 p.m.
Line

Poll Question:

How many times have you been to the Farmers Market this year?

line
Weekly Spotlight
The Wire

The fall edition of The Wire quarterly newsletter has officially arrived in mailboxes! Click HERE to see what's going on in the Village. If you happened not to receive a copy mailed to your residence, please reach out to the Village and let us know. We do have a minor oops on dates in the newsletter, please see the correction below.

oops
Agenda

The Plan Commission meeting will be held on Monday, September 8, 2025, at 6:00 p.m. in the Village Board Room. Click here to see the entire agenda and packet.

Agenda

The Board of Trustees Budget Workshop meeting will be held on Tuesday, September 9, 2025, at 4:00 p.m. in the Village Board Room. Click here to see the entire agenda and packet.

Trustee Vacancy

Are you interested in serving the community by being a member of the Weston Village Board? Due to a recent vacancy, the Village of Weston is currently accepting applications for Village Trustee. Letters of interest and resumes will be accepted until the application deadline of Monday, September 8th at 12:00 p.m.

line
WM closed

With the road construction going on at Fuller St., the Recycling Drop-off at the Waste Management site will be temporarily closed. We will update when it’s available to use again. Thank you for your patience and understanding.

Fall Yard Material Pick-Up Map

The 2025 Fall Yard Pickup is scheduled for the months of October and November, 2025.

Materials MUST be out to the roadside by 7 AM on the scheduled day of pickup. Please click on the map above to see what dates pickup will occur in your neighborhood.

line
Updates

Would you like to be alerted of e-newsletters, agendas that are posted, road construction updates, water main breaks, snow emergencies, etc. in the Village of Weston?  

This is an excellent tool provided to our community to be alerted to various happenings in the community!  The process to get signed up is as follows:

1. Go to www.westonwi.gov
2. Hover over "How Do I" and click "Get Notified"
3. Click "E-Notifications"
4. Type your email in the box and select "Sign In"
5. If you want to  text messages also, enter your phone number and click "save"
6. Scroll down and click the envelope or phone icon or both for whatever you would like to receive.  
7. Click "Save"
8. Don't forget to reply to the email and text message confirmation you will receive to confirm you want to be signed up.

Public Works Report

Updates for current roadway projects:


Schofield Ave (Normandy St to Birch St):
- Week of 9/1: Curb and Gutter is planned to be installed this week along with finishing any remaining utility work. 

-Week of 9/8: Work on sidewalks, driveways and traffic signals is planned for this week along with any remaining curb that wasn't finished the prior week

Weston Ave (CR-X to Ryan St):
- Week of 9/1
: Water and sewer service lateral installation will continue from Heeren going east. Roadway grading will likely start later in the week and there is blasting of rock to still occur east of Lindenwood Ct.

- Week of 9/8: Crews will work on continuing to move east with utilities and follow behind with road building as utility work is completed.

 Fuller St:
- Week of 9/1: Watermain and storm sewer work from Meridian St heading north to Rogan will continue. Yard restoration north of Thomas to begin. Vehicles will be given access back to driveways as well.

- Week of 9/8: Continue with road building behind utility work south of Rogan along with continued water and storm sewer pipe heading towards Rogan.

Business Park Paving (Commerce Dr and Ryan St):
- Week of 9/1: Paving of Commerce Dr from Ryan St to Rickyval St is planned along with structure adjustments on Ryan St.

- Week of 9/8: Finish any concrete repairs on Ryan St and any remaining paving or utility adjustments along Rickyval St.

Asphalt Overlay Projects:
Asphalt overlays are planned for the below streets.  Crews have or will be completing prep work ahead of the overlay paving which includes adjusting all manholes and water valves within the pavement as well as milling along the curb lines or driveways. Paving of these areas is anticipated to be the week of 9/15.

  • Post Ave (West of BUS 51)
  • Cortez, Coronado and Lawndale (North of Jelinek)
  • Terrier and Birchwood Ln (South of Jelinek)
  • Prairie St and Westfair St (West of Mesker)
  • Alex St (West of Sandy Ln)
  • Michael Dr
  • Cheryl Dr
  • Jacob St
  • Twin Pines Ln
  • Morning View (East of Twin Pines)
  • Babl Ln (East of Twin Pines)
  • Saxon Ave
  • Regent St
  • Meridian St
  • Jean Ellen St
  • Sternberg Ave (Scott St to Mesker St)

Shorey Ave Repaving (County Road X to Anastasia Dr): This project is expected to start around 9/2 and last approximately one week.

Weekly updates on roadway projects are released every Friday on Facebook.

We Want Your Feedback! 

Please submit your ideas for our newsletters!

jgebert@westonwi.gov

Line

FOLLOW, LIKE, AND SUBSCRIBE TO OUR SOCIALS! 

Click an icon below to view more

Line
Subscribe to notifications
NEXTDOOR CLICKABLE LINK
Listen to Meetings on Youtube
Farmers Market FB Page
Main FB Page
Weston Aquatic Center FB Page
Share on Facebook
Share on Twitter
Share via Email

Copyright 2023 Weston WI. All Rights Reserved.
4747 Camp Phillips Rd, Weston WI 54476

Powered by
CivicSend - A product of CivicPlus