Updates for current roadway projects:
Schofield Ave (Normandy St to Birch St):
- Week of 9/22: Continue working on street grading, traffic signals and concrete work along the eastbound lanes.
-Week of 9/29: Continue with concrete work, road grading if needed, traffic signals and potentially first layer of asphalt paving.
Weston Ave (CR-X to Ryan St):
- Week of 9/22: Rock drilling and blasting to continue as needed between Lindenwood Ct and Ryan St. Sanitary sewer installation to continue as rock is cleared and watermain to follow behind sanitary installation. Grading to continue where utility work is completed.
- Week of 9/29: Sewer and water installation will continue with road building following utility installation.
Fuller St:
- Week of 9/22: North of Thomas Ave the crew will be working on restoration of grass areas. Then between Schofield Ave and Meridian, curb and gutter will be poured. From Meridian north watermain and storm sewer installation will continue. Pond excavation work will be ongoing at Kellyland Park as well.
- Week of 9/29: Asphalt is planned to be paved from Thomas Ave north to Ross Ave. Pipe work between Meridian and Rogan should be completed with road building to follow. Continued excavation for the storm pond at Kellyland Park will continue as well. Storm sewer work on Rogan Ln possibly starts this week as well.
Business Park Paving (Commerce Dr and Ryan St):
- Week of 9/22: Should be paving final layers of asphalt on both Commerce Dr and Ryan St.
- Week of 9/29: Finish paving Ryan St if needed and then move to the streets around the Hospital.
Asphalt Overlay Projects:Asphalt overlay paving started this past week. Streets remaining are shown below. Crews have completed the prep work ahead of the overlay paving which includes adjusting all manholes and water valves within the pavement as well as milling along the curb lines or driveways. Paving of these areas will continue the week of 9/22.
- Post Ave (West of BUS 51)
- Cortez, Coronado and Lawndale (North of Jelinek)
- Terrier and Birchwood Ln (South of Jelinek)
- Alex St (West of Sandy Ln)
- Michael Dr
- Cheryl Dr
- Jacob St
- Twin Pines Ln
- Morning View (East of Twin Pines)
- Babl Ln (East of Twin Pines)
- Saxon Ave
- Regent St
- Meridian St
Shorey Ave Repaving (County Road X to Anastasia Dr): • Final layer of asphalt is scheduled to be paved Tuesday 9/23.
Weekly updates on roadway projects are released every Friday on Facebook.