Updates for current roadway projects:
Schofield Ave (Normandy St to Birch St):
- Week of 7/7: Final layer of asphalt paving is expected to be completed early in the week with traffic then being shifted to the new lanes by Friday 7/11.
- Week of 7/14: Work begins on the southern lanes with the concrete pavement removal.
Weston Ave (CR-X to Ryan St):
- Week of 7/7: Road building from Von Kanel to Heeren St to continue.
- Week of 7/14: Road building through the Heeren intersection to continue if not finished and then work on sanitary sewer to start up again.
Fuller St:
- Week of 7/7: Continue to install new storm sewer along Fuller heading north from Rogan Ln.
- Water valve and hydrant work is expected to be completed at Thomas and Fuller. on Monday
- Tricia and Fuller on Tuesday
- High Ridge and Fuller on Wednesday
- Morning View and Fuller on Friday
- The crew will continue excavating out the pond at Kellyland Park as well
- Week of 7/14: Continue with storm sewer and water valve/hydrant work heading north to Ross Ave along with continued excavation of the pond at Kellyland Park.
Asphalt Sealing:
- Week of 7/7: Fahrner was rained out for parts of this past week so they’ll be continuing to work through the residential streets this coming week.
Crack Sealing:
- Week of 7/7: Precision Sealcoating will continue crack sealing throughout the Village on various asphalt streets.