Updates for current roadway projects:
Schofield Ave (Normandy St to Birch St):
- Week of 7/14: Traffic will now be on the north side of the median on the new asphalt pavement. This week will include breaking and removing the concrete pavement along the southern lanes as well as working on electrical items for the new traffic signals.
- Week of 7/21: Removal of concrete pavement will continue. Sanitary sewer manhole replacement will start between Normandy St and Alderson St.
Weston Ave (CR-X to Ryan St):
- Week of 7/14: Road building from Von Kanel to Heeren St to continue along with sanitary sewer installation resuming east of Heeren St.
- Week of 7/21: Road building through the Heeren intersection to continue if not finished and sewer work to continue heading east as well.
Fuller St:
- Week of 7/14: Continue to install new storm sewer along Fuller heading north from Rogan Ln along with the below planned water valve and hydrant work.
- Monday 7/14: Replacement hydrant on Tricia
- Tuesday 7/15: Replace valves at Morning View and Fuller
- Wednesday 7/16: Install hydrant at Thomas
- Thursday 7/17: New water valves at the Ross and Fuller intersection.
- The crew will continue excavating out the pond at Kellyland Park as well.
- Week of 7/21: Continue with storm sewer installation heading north to Ross Ave along with continued excavation of the pond at Kellyland Park.
Asphalt Sealing:
- Work was completed as of 7/11.
Crack Sealing:
- Work was completed as of 7/11.
Shorey Ave Repaving (County Road X to Anastasia Dr): This project is still on hold until work on Weston Ave can be completed through the Heeren intersection.
Weekly updates on roadway projects are released every Friday on Facebook.