Updates for current roadway projects:
Schofield Ave (Normandy St to Birch St):
- Week of 11/3: Pavement markings and remaining restoration items to be completed.
Weston Ave (CR-X to Ryan St):
- Week of 11/3: Paving of the road Monday and Tuesday from Von Kanel to Ryan St, then paving the final layer later in the week.
- Week of 11/10: Restoration, pavement markings and other outstanding items.
Fuller St:
- Week of 11/3: Asphalt paving to be completed on Fuller and all side streets. Paving of asphalt driveways to be completed as well. Seeding and restoration to be done too.
- Week of 11/10: Complete other outstanding items.
Hospital Area Paving:
- Week of 11/3: Pulverizing and paving of Weston Ave from Birch St to CR-X.
- Week of 11/10: Finish Weston Ave and work on Birch St.
Weekly updates on roadway projects are released every Friday on Facebook.